2019 Wrap up - Hampden Bridge Legacy Project

4 months ago


August 2019

Levee works near Abutment A are complete which will allow the refurbishment of Abutment A to start.


December 2018 – March 2019

Planning for construction including services, irrigation, landscaping, Abutment A restoration, lighting and signage.

Abutment A before image

Image: A bird's eye view of Abutment A prior to refurbishment


November 2018

Detailed design completed

hampton concept detailed

Image: Somewhere Landscape Architects drawings of the Legacy project design


November 2017

Design updated to align with the design of Stage Two – Levee Bank Upgrade


May 2017

Funding received from Office of Environment & Heritage


March 2017

Concept designs for the Hampden Bridge Legacy Project were approved at the March Ordinary Council Meeting.The project now progresses to the detailed design stage and a Councillor workshop held prior to the next report going to Council.

Hampden Bridge postcard

Image: An image of Hampden Bridge as it appears on a "Greetings from Wagga" postcard, circa 1909


May 2015

Heritage Interpretation Strategy completed