May → June 2019

Design concept released

May → June 2019

Community consultation and public exhibition

July 2019 → June 2020

Engage designer contractor


July 2019 → June 2020

GHD engaged to undertake REF and detail design

July 2019 → June 2020

Site investigations

July 2019 → June 2020

Complete REF and detail design

July 2019 → June 2020

Commence preliminary site clearing works

July 2019 → June 2020

Procurement of D&C contractor

July 2019 → June 2020

Stakeholder engagement activities

July 2020 → June 2021

Construction of works

July → October 2021

Completion and handover